How to price a BOQ with CPWD DSR

To price a BOQ with the CPWD DSR, match each BOQ item to a DSR item, confirm the unit and specification agree, take the DSR rate, adjust it for your location, build a market-rate analysis for items the DSR lacks, then multiply by quantity and total. Read the edition's notes on what the rates include.

What is the CPWD DSR?

The DSR is the Delhi Schedule of Rates, published by the Central Public Works Department of India. It lists analysed rates for civil and electrical work items. Each rate is built from material coefficients, labour constants and plant charges, plus an allowance for contractor's profit and overheads. CPWD publishes a companion Analysis of Rates that shows the build-up behind each item.

A DSR rate is a scheduled estimate rate. It is not a quote and it is not today's market price. That distinction decides how you use it.

Step 1: Fix the edition and the volume

Editions are dated. A tender will usually name the edition or the department's accepted schedule. Use that one. Mixing items from two editions in one estimate produces a total nobody can reconcile.

Step 2: Read the general notes first

The front matter of each edition states what a rate covers. Check these points before pricing a single line:

  • What the rate includes, such as the percentage allowed for contractor's profit and overheads.
  • How GST is handled. The edition's notes say whether rates are exclusive of it.
  • Lead and lift allowances, and any conditions on height or depth.
  • The specification each item assumes.

Step 3: Match BOQ items to DSR items

Read the BOQ description against the DSR item description, including the specification and any grade or mix. A line for "M25 concrete in slab" matches a different DSR item from "M20 concrete in footing". Record the DSR item number beside every BOQ line. That number is your audit trail.

Where two DSR items could fit, take the one that matches the specification, not the one with the lower rate. Note the choice.

Step 4: Check units and measurement

A match on description is not enough. The unit must also match. A BOQ line in square metres against a DSR item per cubic metre needs a stated thickness to convert. Indian practice generally measures to IS 1200, so confirm your quantities follow it, or note where they do not.

Step 5: Adjust for location

DSR rates are Delhi rates. For work elsewhere, CPWD offices may apply a cost index for the station, and many projects use the relevant state Schedule of Rates instead. Which route applies depends on the department and tender, so confirm it with the tender document rather than assuming.

Step 6: Price items the DSR does not cover

Some items have no DSR equivalent: a new material, a proprietary system, an unusual finish. Price these with a market-rate analysis. List the materials, labour and plant for one unit, price each from a quote or a dated source, then add overheads and profit on the same basis the rest of the estimate uses. Mark these lines as non-scheduled so a reviewer can find them.

Step 7: Extend, total and apply the tender basis

Multiply each rate by its quantity and total by section. Then apply taxes as the edition and the tender require. Many CPWD tenders are percentage-rate tenders, where bidders quote a percentage above or below the estimated cost. If yours is one, your final figure is the estimate adjusted by that percentage, so keep the estimate and the percentage separate.

How to do a CPWD DSR rate analysis, step by step

A DSR rate is not a single figure plucked from a list. Each scheduled rate is the output of a rate analysis, and CPWD's Analysis of Rates (AoR) shows how that figure is built. When you price a non-scheduled item, or when you need to defend or recompute a scheduled rate, you repeat the same build-up. The procedure below follows the standard CPWD method for a unit rate.

Step A: Define the unit and the specification

State the item exactly, including the grade, mix, class and finish, and the unit the rate will be expressed in, for example one cubic metre of M20 reinforced cement concrete (1:1.5:3) in foundations. Every coefficient that follows is "per this unit", so the unit must be fixed before any quantity is entered.

Step B: List the material coefficients

Write down the quantity of each material consumed to produce one unit, including an allowance for wastage. These coefficients come from the CPWD DAR (Delhi Analysis of Rates) or the edition's standard data. For one cubic metre of M20 (1:1.5:3) concrete, a typical build-up is:

MaterialCoefficient (per cu m)Basis
Cement~6.34 bags (317 kg)Mix proportion plus wastage
Coarse sand (fine aggregate)~0.44 cu mMix proportion plus 1.5x bulking/voids factor
Coarse aggregate 20 mm~0.88 cu mMix proportion plus voids factor
WaterAs per w/c ratioOften included in rate per edition notes

The figures above are indicative. Always read the coefficients from the edition and AoR you are working to, because they change between editions.

Step C: Price each material and total the material cost

Multiply each coefficient by its basic rate at site, including carriage to the work. Sum the results to get the material cost for one unit. Keep the dated source for every basic rate so the analysis is auditable.

Step D: List the labour constants

Enter the labour required to produce one unit, taken from the AoR labour constants, and price each category at the prevailing wage. For one cubic metre of RCC a typical crew entry reads:

Labour categoryConstant (days per cu m)
Mason (skilled)~0.17
Beldar (unskilled)~1.57
Bhisti (water carrier)~0.90
Mazdoor for mixing/placingPer AoR

Multiply each constant by the daily wage for that trade and total the labour cost.

Step E: Add plant, machinery and sundries

Include the hire or use charge for any plant: a concrete mixer, vibrator, or other equipment the item needs, priced per unit of output. Add sundries such as tools, scaffolding use and minor consumables, usually expressed as a small percentage, per the edition's convention.

Step F: Sum to the prime cost

Add material, labour and plant and sundries. This subtotal is the prime cost of one unit before profit and overheads.

Step G: Add contractor's profit and overheads

Apply the percentage the edition allows, commonly 15 percent in CPWD analyses, on the prime cost. Use the exact figure stated in your edition's general notes, not a remembered one.

Step H: Round and state the rate

Add the percentage to the prime cost to get the analysed rate per unit, then round as the edition directs. State the rate against the unit and specification you fixed in Step A. A worked line for M20 RCC therefore reads: material cost + labour cost + plant/sundries = prime cost; prime cost x 1.15 = analysed rate per cubic metre, exclusive of GST unless the notes say otherwise.

Worked summary of the rate-analysis flow

  1. Fix unit and specification.
  2. Enter material coefficients with wastage.
  3. Price materials at site, including carriage.
  4. Enter labour constants and price at wage rates.
  5. Add plant, machinery and sundries.
  6. Sum to prime cost.
  7. Add contractor's profit and overheads (e.g. 15%).
  8. Round and state the analysed rate against the unit.

This is the same sequence CPWD uses internally, so an estimate built this way reconciles against the published AoR line by line.

Where the work goes wrong

MistakeWhat happensFix
Mixed editionsTotals cannot be traced to one scheduleOne edition per estimate
Matching on description onlyA rate for the wrong grade or unit is appliedCheck specification and unit on every line
Ignoring the notes on GSTTax is counted twice or missedRead the edition's general notes
Unflagged market ratesReviewer cannot tell scheduled from assumedMark non-scheduled lines and keep sources
Coefficients without wastageMaterial cost understates real consumptionUse AoR coefficients that include wastage

How EstimateNext handles this

EstimateNext's rate library for India includes the CPWD DSR and the Schedules of Rates of 20 or more states. When it prices a BOQ, each line shows the rate, its source and a confidence badge, and lines it could not match are flagged for review. Estimators can accept, reject or re-match a suggestion. The rates are indicative and should be verified before tender.

If you want to see this on your own document, the offer below is free.

Send one BOQ. Get it priced in 24 hours. Free.

No card and no sales call first. Any format, any trade.

Price my BOQ

Related

Frequently asked questions

What does CPWD DSR stand for?
Delhi Schedule of Rates, published by the Central Public Works Department of India. It gives analysed rates for civil and electrical work items.
Can I use DSR rates outside Delhi?
They are Delhi rates. Outside Delhi, CPWD offices may apply a cost index for the station, and many projects use a state Schedule of Rates. Check which one your tender specifies.
Are DSR rates inclusive of GST?
Check the general notes of the edition you use. They state how GST is treated, and handling differs between editions, so do not assume.
What do I do for an item that is not in the DSR?
Prepare a market-rate analysis: materials, labour and plant for one unit, priced from dated quotes or sources, then overheads and profit. Mark the line as non-scheduled.
Is the DSR rate the price a contractor will charge?
No. It is a scheduled estimate rate. In a percentage-rate tender, bidders quote a percentage above or below the estimate.
Does EstimateNext include the DSR?
Its India rate library includes the CPWD DSR and 20 or more state Schedules of Rates, with the source shown on each priced line. Rates are indicative; verify before tender.

Upload Your First BOQ — Get a Priced Estimate in Minutes

AI-powered rate matching across 78,000+ items. Free tier, no credit card.